I wanted to inform/update you on some work that is moving very quickly on the Southeast side of Campus. Citizens Water will be installing a new water main from University Boulevard to Blackford Street in New York Street. Below are some key points with highlights for major impacts;
a. Start @ University Boulevard and work East in the Northern most lane of New York to Blackford
b. Start Mobilization and Construction this Thursday 06/27/13 – scheduled for approximately 45 days
c. University Boulevard will be restricted for approximately 1-2 weeks
d. Blackford intersection will need to be shut down and traffic rerouted for approximately 2 weeks
e. Citizens has committed to performing the Blackford shutdown prior to school start
f. Blake Street (North and South side of New York) will be restricted for about 3-4 days as work progresses east
g. Water Service to Buildings will need to be shut down for new connections (schedules to be determined)
↧